What you will build
Build a small project timeline with Milestone, Owner, Start, Due, Progress, and a Status column that updates from a fixed status date.
Prepare the sample data
Open the practice workbook or make a copy, then make sure A1:E4 matches the sample below. Start and Due must be valid dates, and Progress must be a number from 0 to 1.
Practice in your own copy
Make your own Google Sheets copy with the same data, formulas, formatting, filter and frozen header. The original remains unchanged.
Sign in to Google. If the original is not publicly shared, download the full workbook and import it into Google Sheets, or paste the example data into your own sheet.
Open the practice workbook in Google Sheets ↗
Add a status date and Status column
Step 1: Enter Status in F1. Enter Status date in H1 and 2026-10-04 in H2. A fixed date keeps the lesson reproducible instead of changing every day.
Step 2: In F2, enter the formula below.
=IF(E2>=1,"Done",IF(D2<$H$2,"Check timing","In progress"))Step 3: Fill the formula from F2 down through F4. With the sample data and Status date 2026-10-04, the results are Done, Check timing, and In progress.
Test a changed input
Step 4: Temporarily change Design Progress in E3 from 0.5 to 1. F3 should change from "Check timing" to "Done". After verifying it, restore E3 to 0.5.
Checkpoint
| Milestone | Owner | Start | Due | Progress | Status |
|---|---|---|---|---|---|
| Brief | An | 2026-09-21 | 2026-09-23 | 1 | Done |
| Design | Binh | 2026-09-24 | 2026-09-30 | 0.5 | Check timing |
| QA | Chi | 2026-10-01 | 2026-10-05 | 0 | In progress |
These results use Status date 2026-10-04. If you change H2, incomplete milestones may return a different status.
Common mistakes and fixes
If a status looks wrong, check three things: Due is a valid date, Progress is a number from 0 to 1, and H2 contains the intended status date.
Independent practice
Add a fourth milestone with valid Start/Due dates, fill the Status formula into the new row, then test both an incomplete Progress value and Progress = 1 to verify both branches of the formula.
Key takeaways
- ✓The sample timeline uses Milestone, Owner, Start, Due, Progress, and Status.
- ✓A fixed status date keeps the result reproducible and easy to verify.
- ✓The formula checks Progress >= 1 before it evaluates Due.
- ✓The $H$2 reference must stay fixed when the formula is filled down.
- ✓Changing one input and restoring it confirms that the formula responds correctly.
Check your understanding
Answer four questions about the practice sheet.
Continue learning
Previous lesson: Invoice tracker; Next lesson: Content calendar.
Comments
No comments yet. Be the first to join the discussion.